"""Draw paired original schedule bars; write the matching PNG basename to cwd.
Run from _media. Tested with Python 3.14.4 and Matplotlib 3.10.7.
"""
from pathlib import Path
import matplotlib
matplotlib.use("Agg")
import matplotlib.pyplot as plt
from matplotlib.patches import Patch
def main():
tasks = list("ABCDEF")
durations = dict(zip(tasks, [3, 2, 4, 2, 3, 1]))
predecessors = {"A": [], "B": ["A"], "C": ["A"],
"D": ["B", "C"], "E": [], "F": ["D", "E"]}
early = {}
for task in tasks:
early[task] = max((early[p] + durations[p]
for p in predecessors[task]), default=0)
finish = max(early[t] + durations[t] for t in tasks)
successors = {t: [] for t in tasks}
for task, parents in predecessors.items():
for parent in parents:
successors[parent].append(task)
late = {}
for task in reversed(tasks):
late[task] = min((late[s] for s in successors[task]),
default=finish) - durations[task]
floats = [late[t] - early[t] for t in tasks]
assert finish == 10 and floats == [0, 2, 0, 0, 6, 0]
teal, blue, ink = "#007b78", "#476c9c", "#203548"
fig, ax = plt.subplots(figsize=(9.0, 6.0), dpi=120, facecolor="white")
ax.set_facecolor("white")
centers = list(range(5, -1, -1))
for task, y, slack in zip(tasks, centers, floats):
color = teal if slack == 0 else blue
# Two separate tracks make coincident critical bars visible too.
early_y, late_y, height = y + 0.20, y - 0.20, 0.25
ax.barh(early_y, durations[task], left=early[task], height=height,
color=color, edgecolor=color, linewidth=1.5, zorder=3)
ax.barh(late_y, durations[task], left=late[task], height=height,
facecolor="white", edgecolor=color, linewidth=1.8, zorder=3)
ax.text(early[task] + durations[task] / 2, early_y,
f"{early[task]}–{early[task] + durations[task]}",
ha="center", va="center", fontsize=9, color="white", zorder=4)
ax.text(late[task] + durations[task] / 2, late_y,
f"{late[task]}–{late[task] + durations[task]}",
ha="center", va="center", fontsize=9, color=color, zorder=4)
if slack:
bracket_y = y - 0.42
ax.plot([early[task], late[task]], [bracket_y, bracket_y],
color=color, linewidth=1.3, zorder=4)
ax.vlines([early[task], late[task]], bracket_y - 0.05,
bracket_y + 0.05, color=color, linewidth=1.3, zorder=4)
ax.text(10.32, y, str(slack), ha="center", va="center",
fontsize=12, color=color, fontweight="bold")
ax.axhline(y - 0.50, color="#e6eaef", lw=0.8, zorder=0)
ax.axvline(finish, color=ink, linestyle="--", lw=1.5, zorder=2)
ax.text(10.32, 5.60, "Float", ha="center", va="center",
fontsize=10, color=ink)
ax.set(yticks=centers, yticklabels=tasks, xticks=range(11),
xlim=(-0.15, 10.65), ylim=(-0.65, 5.7), xlabel="Time units")
ax.tick_params(axis="both", labelsize=11, length=0, pad=7)
ax.grid(axis="x", color="#e2e8ee", linewidth=0.8, zorder=0)
for spine in ax.spines.values():
spine.set_visible(False)
ax.set_title("Same project finish: earliest and latest schedules",
fontsize=15, color=ink, pad=40)
ax.legend(handles=[Patch(facecolor=blue, edgecolor=blue,
label="Earliest (solid)"),
Patch(facecolor="white", edgecolor=blue,
label="Latest (hollow)"),
Patch(facecolor=teal, edgecolor=teal,
label="Critical activity (float 0)")],
loc="lower center", bbox_to_anchor=(0.5, 1.01),
ncol=3, frameon=False, fontsize=9.5)
fig.text(0.5, 0.035,
"Paired tracks show separate schedules. Brackets mark start-time shifts; finish = 10.",
ha="center", fontsize=10, color=ink)
fig.subplots_adjust(left=0.07, right=0.97, bottom=0.15, top=0.81)
output = Path.cwd() / Path(__file__).with_suffix(".png").name
fig.savefig(output, facecolor="white", transparent=False)
plt.close(fig)
print(f"{output.name}: starts {list(early.values())}, "
f"latest {list(late[t] for t in tasks)}, floats {floats}")
if __name__ == "__main__":
main()