= Solution
Assume job sizes $t_i\geq0$ and machine speeds $s_j>0$, with at least one machine. Let $y_{ij}\geq0$ be the amount of job $T_i$ assigned to machine $M_j$, and let $T\geq0$ be the proposed <makespan>. Use the <linear program>
$$
\boxed{
\begin{aligned}
\min\quad&T\\
\text{subject to}\quad&\sum_{j=1}^m y_{ij}=t_i&& (1\leq i\leq n),\\
&\sum_{i=1}^n y_{ij}\leq s_jT&& (1\leq j\leq m),\\
&y_{ij}\geq0&& (1\leq i\leq n,\ 1\leq j\leq m),\\
&T\geq0.
\end{aligned}}
$$
The first family of constraints assigns every job completely. The second bounds each machine's completion time by $T$, since $L_j/s_j\leq T$ is equivalent to $L_j\leq s_jT$. It is a <linear inequality> because $s_j$ is an input constant. There is no integrality restriction: jobs are divisible as specified in this <scheduling> model.
To verify the formulation, any actual allocation defines the variables above, with $T$ equal to its largest completion time, and satisfies every constraint. Conversely, from a <feasible solution>, assign amount $y_{ij}$ to machine $M_j$ and process its assigned pieces consecutively. Its total time is at most $T$, so the <linear program> realizes the claimed <makespan>.
There is also a useful exact check. Put $W=\sum_i t_i$ and $S=\sum_j s_j$. Summing machine constraints gives $W\leq ST$, so $T\geq W/S$. Assigning
$$
y_{ij}=t_i\frac{s_j}{S}
$$
makes every machine's completion time $W/S$, proving
$$
\boxed{T^*=\frac{\sum_i t_i}{\sum_j s_j}.}
$$
This relies on the paper's divisible-work model, in which machine completion times depend only on total assigned size. If $W=0$, the optimum is $0$.