= Solution
The total processing time $\sum_{i=1}^{40}t_i$ is constant for a single machine, so only the initial setup and changeover sum depends on the order. Use the <dummy-job reduction for sequence-dependent setup times>. Add <vertex> $0$, and set
$$
c_{0i}=s_i,\qquad c_{ij}=s_{ij}\quad(i,j\ne0,\ i\ne j),
\qquad c_{i0}=0.
$$
Let the binary variable $x_{ij}$ indicate that $j$ follows $i$ in the augmented tour. A <Hamiltonian cycle> through $0$ specifies exactly one schedule, read starting after $0$. An exact <integer programming> formulation is
$$
\boxed{\begin{aligned}
\min\quad&\sum_{i=1}^{40}t_i+
\sum_{\substack{i,j\in\{0,\ldots,40\}\\i\ne j}}c_{ij}x_{ij}\\
\text{subject to}\quad&
\sum_{j\ne i}x_{ij}=1\quad(i=0,\ldots,40),\\
&\sum_{i\ne j}x_{ij}=1\quad(j=0,\ldots,40),\\
&\sum_{\substack{i,j\in S\\i\ne j}}x_{ij}\leq |S|-1
\quad(\varnothing\ne S\subsetneq\{0,\ldots,40\}),\\
&x_{ij}\in\{0,1\}.
\end{aligned}}
$$
The degree equations alone describe a <cycle cover of a directed graph>, possibly several separate <graph cycles>. The <subtour elimination constraints> exclude every proper directed <graph cycle>; the cover is therefore a single tour through all jobs. Conversely every schedule supplies a feasible tour with exactly its completion time as objective. Exponentially many written inequalities are permitted in this exact formulation; an implementation may add them only when violated.
For three parallel machines, the relevant objective is the <parallel-machine makespan with sequence-dependent setups>, not simply total setup cost. Partition jobs into three ordered lists $\pi_r$. For a nonempty list define
$$
C_r=s_{\pi_r(1)}+\sum_{i\in\pi_r}t_i+
\sum_{h=1}^{|\pi_r|-1}s_{\pi_r(h),\pi_r(h+1)};
$$
an empty machine has $C_r=0$. Minimize $C_{\max}$ subject to $C_r\leq C_{\max}$ for each machine and each job assigned once. This can be written as a mixed-integer extension with assignment variables, one dummy tour per machine and conditional subtour cuts.
A practical strategy starts with a balanced assignment, sequences each machine using the single-machine methods, and improves by relocating or swapping jobs between machines together with within-machine <2-opt> moves. Score each move by its change in $\max_r C_r$. <Branch and bound> can combine machine-assignment decisions with within-machine assignment bounds. For nonnegative times, the total processing time divided by three and the largest individual processing time are valid lower bounds, supplemented by setup-dependent route bounds. \b[Balancing processing and changeovers jointly is essential; independently minimizing the three tour costs does not by itself minimize completion time.]