= Solution
In a <minimum-cost flow> problem, every directed arc $(i,j)$ has a per-unit cost $c_{ij}$ and lower and upper capacities $\ell_{ij},u_{ij}$. Each vertex has a prescribed net supply $b_i$, with $\sum_i b_i=0$. We seek flows minimizing $\sum_{ij}c_{ij}f_{ij}$ subject to the <flow conservation> equations
$$
\sum_jf_{ij}-\sum_jf_{ji}=b_i,\qquad
\ell_{ij}\leq f_{ij}\leq u_{ij}.
$$
The <uncapacitated minimum-cost flow> case has $u_{ij}=\infty$ and, here, $\ell_{ij}=0$.
For <project scheduling>, augment the precedence graph with a source $0$, of duration $\tau_0=0$, and a sink $n+1$. Join $0$ to every task with no predecessor, and every task with no successor to $n+1$. Extend the precedence matrix to these dummy arcs. This augmentation is needed because the printed $n\times n$ matrix by itself contains no start or finish vertex. Assuming the precedence graph is a <Directed acyclic graph>, every task lies on a source-to-sink path. Unlimited parallel work then gives the <linear programming> formulation
$$
\boxed{\min(t_{n+1}-t_0),\qquad
t_j-t_i\geq\tau_i\quad\text{for every augmented arc }(i,j).}
$$
The time variables are unrestricted; a common translation changes nothing, so we may fix $t_0=0$. These inequalities say that each successor starts after its predecessor finishes. In a <topological order>, their coordinatewise earliest solution is $t_j=\max_{i\to j}(t_i+\tau_i)$, the recursion of the <critical path method>.
To derive <project scheduling duality>, associate a nonnegative multiplier $f_{ij}$ with $\tau_i+t_i-t_j\leq0$. The <Lagrangian> is
$$
L(t,f)=t_{n+1}-t_0+\sum_{(i,j)}f_{ij}(\tau_i+t_i-t_j).
$$
Its infimum over the free time variables is finite precisely when the coefficients of all $t_i$ vanish. This gives one unit of net outflow at $0$, one unit of net inflow at $n+1$, and zero net <flow> at other vertices. Hence the dual is
$$
\max\sum_{(i,j)}\tau_i f_{ij}
\quad\text{subject to }f\geq0
\text{ and a unit flow from }0\text{ to }n+1.
$$
Equivalently, minimize $\sum c_{ij}f_{ij}$ with $c_{ij}=-\tau_i$. \b[The project duration is the negative of the optimal minimum-cost <flow> value.] The sign is essential: the dual of the minimization problem maximizes total duration, selecting a longest precedence path.
The <network simplex algorithm> is a general method for <minimum-cost flow>. After shifting lower bounds to zero, first find a feasible <flow>, using artificial arcs and a phase-one objective if needed. A <network simplex tree basis> fixes each non-tree arc at a bound and determines the tree flows by <flow conservation>. Choose <network dual potentials> $\pi_i$ making the <network reduced cost>
$$
r_{ij}=c_{ij}-\pi_i+\pi_j
$$
zero on the tree. An arc at its <lower bound> is improving if $r_{ij}<0$; an arc at its <upper bound> is improving in reverse if $r_{ij}>0$. Adding that residual arc creates one <fundamental cycle>. Increase <flow> around this cycle until an arc reaches a bound, then exchange the entering and leaving tree arcs, or flip the entering arc to its other bound. The <flow conservation> equations remain satisfied. Use an anti-cycling rule for degenerate pivots. If a negative-cost residual cycle has no finite limiting capacity, the objective is unbounded below; if phase one cannot remove artificial <flow>, the problem is infeasible. Otherwise, termination with no negative residual <network reduced costs> certifies optimality, since potentials cancel around cycles and every residual <network circulation> has nonnegative cost.
For this project the augmented arcs are
$$
(0,1),(0,2),(1,3),(2,4),(3,5),(4,5),(4,6),(5,7),(6,7).
$$
In the specified initial <spanning tree>, the unique unit-flow path is $0\to1\to3\to5\to7$. The <flow> on its arcs is one and that on all other tree arcs is zero. Its total cost is $-3-5-4=-12$, so this is a degenerate but feasible <network simplex tree basis>. Normalizing $\pi_0=0$, the tree equations give
$$
(\pi_0,\ldots,\pi_7)=(0,0,-2,3,2,8,8,12).
$$
There are two nonbasic arcs. Their <network reduced costs> are
$$
r_{02}=0-\pi_0+\pi_2=-2,\qquad
r_{67}=-3-\pi_6+\pi_7=1.
$$
Bring $(0,2)$ into the tree. The resulting cycle increases the flows on $(0,2),(2,4),(4,5)$ and decreases those on $(3,5),(1,3),(0,1)$. The three decreasing arcs initially carry one unit, so the maximal step is one. Resolve the leaving-arc tie by removing $(0,1)$. The resulting unit <flow> follows $0\to2\to4\to5\to7$ and has cost $-4-6-4=-14$.
For the new tree, normalized potentials are
$$
(\pi_0,\ldots,\pi_7)=(0,2,0,5,4,10,10,14).
$$
The only nonbasic arcs now have $r_{01}=2$ and $r_{67}=1$, both nonnegative. All tree <network reduced costs> vanish, proving optimality after this single pivot. The earliest feasible schedule, obtained by the <critical path method>, is
$$
\boxed{(t_0,t_1,t_2,t_3,t_4,t_5,t_6,t_7)
=(0,0,0,3,4,10,10,14),\qquad T^*=14.}
$$
The path $2\to4\to5$ has duration $4+6+4=14$, so it and the timetable furnish a <unit-flow certificate for project duration>.