Task float, also called total float or task slack, measures an activity's available start-time delay relative to its earliest start, while allowing a feasible schedule that meets the fixed project finish. For earliest start , latest start , and fixed duration , it is
In the six-activity project scheduling example with start zero and finish 10, B has task float 2 and E has task float 6. B can move from the interval to , and E from to , without changing D's or F's earliest starts. A, C, D, and F have zero task float. With the finish fixed to the optimal duration and the basic critical path method assumptions, zero task float identifies exactly the activities lying on at least one critical graph path. See Hendrickson, §10.4, Activity Float and Schedules.
Task float is not generally an independent allowance that can be spent separately on every activity. For a small example, let two duration-1 activities X then Y form one chain, running in parallel with a separate duration-4 activity. The optimal finish is 4. X has earliest/latest starts 0/2 and Y has earliest/latest starts 1/3, so each has task float 2. Delaying X to 2 forces Y to start at 3, using Y's allowance too. Choosing X at its latest start 2 and Y at its earliest start 1 violates precedence, although both chosen times lie inside their individual ranges. The optimization constraints still couple the decisions. Here B and E can both use their full task floats together because they lie on separate branches; that freedom must be checked from the Directed acyclic graph.

Articles by others on the same topic (NaN)

There are currently no matching articles.