Edge coloring as scheduling

ID: edge-coloring-as-scheduling

Suppose each job occupies two distinct resources for one whole slot, and each resource can serve at most one job in that slot. Make resources vertices and jobs edges. Two jobs conflict exactly when their edges share a vertex, so a valid schedule is a proper edge colouring. Each slot is a matching in a graph; the chromatic index is the minimum number of slots. The colour labels specify the slots, rather than physical colours. This model assumes all jobs are available initially, with equal duration, interchangeable slots and no additional conflicts. The school-timetable motivation in Graph Theory by Reinhard Diestel (author-hosted Colouring preview, opening paragraphs, pp. 123–124) uses this resource-pair interpretation.
Here is a complete example. Two technicians must each use three instruments once. Each job needs its technician and its instrument simultaneously. The six jobs are the edges of the complete bipartite graph :
Within each , the two jobs use different technicians and different instruments, so is a matching in a graph. The three matchings in a graph together cover every job exactly once. Technician has three jobs, so fewer than three slots cannot suffice; the displayed schedule uses three. This is an optimal proper edge colouring with chromatic index three, witnessed by both a schedule and a resource-workload lower bound.
Figure 1.
Six jobs on a complete bipartite graph become three scheduling slots, each a matching in a graph
. The vertices are resources, and each numbered edge is one job. The slot table uses the same colour labels as the proper edge colouring. A technician or instrument appears at most once within a column. Crossings of drawn edges introduce no resource and no conflict. Details.
Repeated jobs requiring the same resource pair become distinct parallel edges of a multigraph, rather than one edge. Additional restrictions change the problem: prescribed allowed slots lead to list edge coloring, while unequal durations, deadlines, or jobs needing more than two resources require a richer scheduling model. Selecting a largest matching in a graph solves a single-round question; a shortest complete schedule must organize all jobs across rounds.