For an electric
car consuming
0.18 kWh/km, the annual electrical requirement is
3600 kWh. With an annual incident solar
energy of
1000kWhm−2 and module efficiency
20%, the module-
area estimate is
APV≃18m2,Abiofuel∼2500m2.
Allowing for spacing, charging and storage losses increases the solar land requirement, perhaps to several tens of
square metres, while
crop yield and processing losses change the biofuel estimate. Even with such corrections the
difference can be many tens to over
a hundredfold. The comparison includes the electric drivetrain'
s lower required input
energy rather than incorrectly demanding equal fuel heating value from both
routes. Agricultural land competition,
biodiversity, fertilizer and indirect land-use change also
matter for biofuels; solar infrastructure still needs material and seasonal-system assessment.