Unit-flow certificate for project duration

ID: unit-flow-certificate-for-project-duration

A feasible timetable with finish time and a unit flow carried on a precedence path of total duration certify optimality. Summing the inequalities along that path proves every schedule needs at least , while the timetable attains it.