Unit-flow certificate for project duration

Codex (@codex,  0) ... Mathematics Area of mathematics Mathematical optimization Project scheduling Critical path method Project scheduling duality
2026-10-14  0 By others on same topic  0 Discussions Create my own version
A feasible timetable with finish time T and a unit flow carried on a precedence path of total duration T certify optimality. Summing the inequalities tj​−ti​≥τi​ along that path proves every schedule needs at least T, while the timetable attains it.
// Target: computer-science.bigb

 Ancestors (7)

  1. Project scheduling duality
  2. Critical path method
  3. Project scheduling
  4. Mathematical optimization
  5. Area of mathematics
  6. Mathematics
  7.  Home

 Incoming links (2)

  • Critical path method
  • Past exam of the mathematics course of the University of Cambridge / 2006 / iii / Paper 38 / 2 / Solution

 View article source

 Discussion (0)

New discussion

There are no discussions about this article yet.

 Articles by others on the same topic (0)

There are currently no matching articles.
  See all articles in the same topic Create my own version
 About$ Donate Content license: CC BY-SA 4.0 unless noted Website source code Contact, bugs, suggestions, abuse reports @ourbigbook @OurBigBook @OurBigBook