Critical path method 2026-10-14
The critical path method calculates an earliest schedule, a latest schedule for a chosen finish time, and each activity's task float. A critical path is a start-to-finish graph path whose total duration is greatest. There can be several such graph paths, and every one constrains completion. In the six-activity project scheduling example, the critical graph path is A-C-D-F, of duration .
Add a zero-duration source before every initial activity and a zero-duration sink after every terminal activity. Give each edge weight , including zero weight on edges leaving . This produces a weighted graph in which a graph path's weight counts every activity on it exactly once. The possible source-to-sink graph paths in our example, omitting the dummy endpoints, are A-B-D-F with weight 8, A-C-D-F with weight 10, and E-F with weight 4.
Every feasible schedule must accommodate each of these sequential chains. Consequently,This bound applies to all source-to-sink graph paths, not just the one we happen to inspect. The critical path method attains the bound by setting each activity's earliest start to the maximum of its predecessors' earliest finish times:Evaluate this recurrence in a topological order, obtained by topological sorting. Each satisfies every incoming optimization constraint, so these times form a feasible solution. The same recurrence calculates the greatest weight of a graph path from to ; hence the feasible finish matches the lower bound. This is dynamic programming on a Directed acyclic graph, rather than an enumeration of all graph paths. See Paul Johnson, Scheduling and longest paths, longest-path algorithm. The linear programming formulation and its certificate are developed in project scheduling duality and unit-flow certificate for project duration.
For our project scheduling example, , , and the two merges giveF finishes at 10. All six activities are completed, even though E is absent from the critical graph path. Recording which predecessor attains each maximum lets us trace a critical graph path backward from the sink; retaining tied choices exposes multiple critical graph paths.
Now fix the project start at zero and the finish at . The latest starts come from a backward pass in reverse topological order:Every activity must finish by the earliest of its successors' latest starts, explaining the minimum here. This gives , , , , , and . These latest times themselves form a feasible solution finishing at 10. The backward calculation depends on the chosen finish time; a later deadline would give different latest times and task floats. The forward and backward passes are described in Olivier de Weck, MIT ESD.36 Lecture 2, slides 22–29.
Earliest solid and latest hollow activity bars for the critical path method, with task floats of 2 for B and 6 for E
. Details. Changing a duration can change which graph paths are critical. If B's duration becomes 4, A-B-D-F and A-C-D-F both take 10: there are two critical graph paths. Shortening C alone then cannot reduce the finish time, because the chain through B still takes 10. If B's duration instead becomes 5, the earliest starts of D and F become 8 and 10, and the finish becomes 11. A-B-D-F is now the unique critical graph path; C has task float 1 relative to that new optimal finish. These calculations show why the critical path method is useful for understanding where a duration change matters, even in a project containing many parallel activities.
Directed acyclic graph Created 2026-09-24 Updated 2026-10-13
A Directed acyclic graph is a directed graph with no directed cycle: following its directed edges can never return to the starting vertex. A directed edge can represent the requirement that task finish before task starts. A directed path then records a chain of prerequisites. The essential prerequisite for topological sorting is that these requirements contain no circular dependency. For finite directed graphs, this is equivalent to the existence of a topological order. [ref]
https://live.ocw.mit.edu/courses/6-006-introduction-to-algorithms-spring-2020/d9265b3b33d238ff914b0223ac8e7628_MIT6_006S20_r10.pdf. MIT, Introduction to Algorithms, Recitation 10, p. 3: directed acyclic graphs and topological sorts
Consider an invented publishing workflow with five tasks: drafts the text, draws a figure, reviews the text, lays out the text and figure, and publishes the result. Its directed edges are , , , , and . Reviewing needs the draft; layout needs both the draft and figure; publication needs both review and layout. The drawing below encodes only these prerequisites, with no measured durations or resource constraints.
Five toy publishing tasks and all five valid topological orders
. Details. The Directed acyclic graph leaves room for choice: and can occur in either order, and after both are complete, and can occur in either order. Task may even precede , since the review does not need the figure. A topological order turns these local prerequisites into a complete executable list while retaining this freedom. It supplies a feasible sequential plan; task durations, available workers, and earliest finishing times require additional information.
Kahn's algorithm 2026-10-14
Kahn's algorithm maintains each remaining vertex's indegree, the number of its unfinished incoming directed edges, and a FIFO queue of ready vertices. Initialize the counts by scanning all directed edges and enqueue every vertex of indegree zero. Repeatedly dequeue a vertex , append it to the output, and decrement the count of each destination in 's adjacency list. Enqueue exactly when its count becomes zero. When the FIFO queue empties, accept the output if it contains all vertices; otherwise report a directed cycle. [ref]
https://raw.githubusercontent.com/kevin-wayne/algs4/master/src/main/java/edu/princeton/cs/algs4/TopologicalX.java. Sedgewick and Wayne, TopologicalX: queue-based topological sorting
Computed ready-queue trace and the obstruction caused by a reverse dependency
. Details. In the displayed run, initialize the FIFO queue as and visit 's destinations in the order . Removing makes ready but leaves waiting for . Removing then makes ready. Publication becomes ready only after both and are removed. The output is ; choosing ready vertices differently can produce the other topological orders. For the modified directed graph with , the same procedure emits and then stops with still waiting on each other.
The invariant is that each stored indegree counts incoming directed edges from unprocessed vertices. A ready vertex therefore has every prerequisite already in the output. If the FIFO queue empties with vertices left, every remaining vertex has a predecessor in the remaining directed graph; the predecessor argument gives a directed cycle. The unprocessed vertices can also include tasks blocked downstream of a directed cycle, so the leftover list alone is not a list of exactly the cyclic vertices.
With adjacency lists, constant-time array access and counter updates, and constant-time FIFO queue operations, the time complexity is in Big O notation. Initialization scans all vertices and directed edges; each vertex is then enqueued at most once and each outgoing directed edge processed at most once. Counts, ready FIFO queue, and output need storage beyond the adjacency lists. Shifting an array on every dequeue invalidates this bound. [ref]
https://raw.githubusercontent.com/kevin-wayne/algs4/master/src/main/java/edu/princeton/cs/algs4/TopologicalX.java. Sedgewick and Wayne, TopologicalX: time and extra-space bounds
[ref]https://raw.githubusercontent.com/kevin-wayne/algs4/master/src/main/java/edu/princeton/cs/algs4/Digraph.java. Sedgewick and Wayne, Digraph: adjacency lists and outgoing-edge iteration
The name refers to A. B. Kahn's 1962 paper "Topological sorting of large networks", published in Communications of the ACM, volume 5, issue 11, pages 558–562. Its abstract motivates topological sorting through network analysis and project planning. [ref]
https://doi.org/10.1145/368996.369025. Kahn, Topological sorting of large networks (1962): publisher's record and abstract
// Target: foundations-of-mathematics.bigb
Topological order 2026-10-14
A topological order of a finite directed graph is a sequence containing every vertex exactly once, withThus every directed edge points forward in the list. Equivalently, a bijection assigning positions satisfies for every directed edge . A topological ordering names the same kind of list. [ref]
The toy Directed acyclic graph has exactly five topological orders: , , , , and . These lists were checked by enumerating all permutations and retaining precisely those satisfying all five directed edge inequalities. Every list ends with , since all other tasks have a directed path to publication. A topological order need not put adjacent entries next to one another in the directed graph: and are consecutive in without a directed edge between them.
A directed cycle would force the impossible chain of position inequalities . In the toy example, adding requires review before publication and publication before review, so there are no topological orders. Together with the construction in topological sorting, this proves that a finite directed graph admits a topological order if and only if it is a Directed acyclic graph. The empty directed graph has the empty sequence as its topological order.
There is also a useful connection to partial orders: define when or there is a directed path from to . For a Directed acyclic graph, this reachability relation is a partial order, and its linear extensions are exactly the topological orders. The Directed acyclic graph specifies which pairs must be ordered; a topological order chooses positions for all the remaining pairs.
Topological ordering Created 2026-09-24 Updated 2026-10-14
A topological ordering is a topological order: a list containing every vertex once and placing the source of every directed edge before its destination. In the parent-and-child language of a Directed acyclic graph, every parent precedes every child, and hence every ancestor precedes every descendant along a directed path. This is an ordering of the vertices, whereas topological sorting is the task of finding it. See topological order for the precise position condition and Kahn's algorithm for a construction.
Topological sorting 2026-10-14
A topological sorting is the task of constructing a topological order of a finite directed graph, or reporting that a directed cycle makes one impossible. Kahn's algorithm repeatedly takes a vertex with no unfinished prerequisites. This is useful whenever an operation consumes results produced by earlier operations: once a vertex is reached in a topological order, every prerequisite along a directed path has already been processed. [ref]
The reason a choice is always available in a nonempty finite Directed acyclic graph is simple. If every vertex had an incoming directed edge, repeatedly following predecessors would eventually revisit a vertex, giving a directed cycle. Removing a vertex and its incident directed edges cannot create a directed cycle, so the argument repeats until every vertex is listed. This proves existence of a topological order and explains why finiteness matters to this procedure.