Assume job sizes and machine speeds , with at least one machine. Let be the amount of job assigned to machine , and let be the proposed makespan. Use the linear programThe first family of constraints assigns every job completely. The second bounds each machine's completion time by , since is equivalent to . It is a linear inequality because is an input constant. There is no integrality restriction: jobs are divisible as specified in this scheduling model.
To verify the formulation, any actual allocation defines the variables above, with equal to its largest completion time, and satisfies every constraint. Conversely, from a feasible solution, assign amount to machine and process its assigned pieces consecutively. Its total time is at most , so the linear program realizes the claimed makespan.