Primary measurement standard 2026-11-05
A primary measurement standard is a measurement standard established by a primary reference measurement procedure, or an artifact selected by convention. A primary reference measurement procedure obtains its result without calibration against a standard of the same kind of quantity; it may still require measurements of other kinds of quantity.[ref]
For an original ideal pressure realization, independently established force acts on an effective piston area . The measurement model givesIf the inputs have independent standard uncertainties and , first-order propagation of uncertainty givesso . This is an illustrative model, not a complete piston-gauge uncertainty budget: a physical realization must also account for effects such as piston deformation and friction.[ref]
The essential distinction is how the pressure value is established. Merely comparing a gauge with another pressure gauge does not make it a primary measurement standard. Primary status also does not mean zero measurement uncertainty.
Primary reference measurement procedure 2026-11-05
A primary reference measurement procedure determines a result without calibration against a measurement standard for a quantity of the same kind. It can still depend on calibrated measurements of other quantities. The VIM example determines delivered liquid volume from a mass difference and liquid mass density, rather than comparing it with another calibrated delivered volume.[ref]
For an original ideal calculation, let the receiving vessel's tare mass be and its gross mass after delivery be . Suppose the liquid's mass density at the measurement conditions is . ThenWith independent standard uncertainties and ,so . These are stipulated values, not a recommended liquid or an actual calibration result.[ref]
The physical procedure would weigh the receiver before and after delivery, establish the liquid temperature and density, and include significant corrections in its measurement model. Evaporation, buoyancy and correlated mass readings can invalidate the simplified expression above. Primary describes the reference relation, not freedom from measurement uncertainty or the absence of any instrument calibration. Its primary status is therefore a claim about the complete procedure, not about this equation alone.