For , the inequality-constrained Karush-Kuhn-Tucker conditions areUnder an appropriate constraint qualification, the second-order necessary condition is on the critical coneEquivalently active constraints with positive multiplier require , while active zero-multiplier constraints retain . Inactive constraints impose no first-order tangent restriction. This distinction is why the relevant cone need not be the nullspace of every active row.
On the strictly feasible region , the logarithmic barrier objective isWith , its gradient isThe positive coefficients are the barrier's multiplier estimates.
The equation , together with and , is the perturbed Karush-Kuhn-Tucker conditions: stationarity is unchanged, while exact complementary slackness becomes for each . A finite limit of such points as satisfies the original conditions by continuity.
For a strictly feasible , the second block uniquely specifies . Substitution into the first block gives precisely . Thuswithin the stated strictly positive domain. These are stationary barrier points; they need not all be local minimizers in a nonconvex problem.
The Jacobian matrix of in isThe top-left block is the Hessian matrix of with held fixed. In the second block, differentiating in gives and in gives . The explicit derivative with respect to is . Differentiate by the chain rule:All blocks are evaluated on the current central path point.
At the current exact path point , stationarity is already zero and . Therefore . Its Newton correction solvesThe matrix has no explicit dependence on the barrier parameter, so comparison with part (iv) giveswhen is nonsingular. If it is singular, the displayed vector is still a solution of the correction equations, but uniqueness of the correction cannot be inferred from differentiability of the path alone.
This step is exactly the tangent predictor in the stated first-order Taylor expansion. For nearby positive , it approximates the new path point with error ; a bounded second path derivative improves this to . Continuity also preserves strict positivity for sufficiently small parameter changes. Larger changes may require damping to keep both the constraint values and multiplier estimates positive.